Input |
|
|
|
Reference drawings,
photographs, hand sketches,
drafting standards, guidelines |
|
|
|
Output |
|
|
|
Detailed drawings for
fabrication along with
local detailing of key
areas, welding details,
instructions to
fabricators, weight
estimates of individual
sections and components |
|
|
|
|
|
Structural analysis
tasks carried out on
Jack-up Projects |
|
|
|
|
 |
Stress Analysis of SBOP
Lift Ring (different
cases, three projects) |
|
|
 |
Spud Tank Analysis for
increased loading,
interpretation of
results and suggestions
for modifications (three
different cases of
penetration) |
|
|
 |
Fairlead modeling and
analysis for a sem-submersible
Detailed design &
Production drawings |
|
|
|
|
|
Detailed design &
Production drawings |
|
|
|
|
|
|
 |
Spud tank Top, Bottom &
Rack post Connecting
Structure |
|
|
 |
Spud tank Structure
Layout |
|
|
 |
Spud tank details of
Bottom tank Segment |
|
|
 |
BOP Lift Ring for
30”BOP/Diverter Plan and
Details
|
|
|
 |
BOP Lift Ring for
30”BOP/Diverter Sections
and Details |
|
|
 |
Cantilever Beam Fwd End
Extension (12’)
Elevation and Details |
|
|
 |
Cantilever Beam Fwd End
Extension (12’)
Elevation and Sections |
|
|
 |
Cantilever Beam Fwd End
Extension (12’) Sections
and Details |
|
|
 |
AFT Burner Boom(PORT)
Plans and Details |
|
|
 |
AFT Burner Boom (PORT)
Plan, Sections Details |
|
|
 |
Burner Boom Foundation
Sections & Details |
|
|
 |
Burner Boom Access
Platforms Plan, Section
and Elevation |
|
|
 |
Burner Boom Foundation
Plans and Elevation |
|
|
 |
Burner Boom Access
Platforms Plan, Sections
and Details |
|
|
 |
MLT 116C Leg mounted JIB
crane (5-Ton capacity)
Elevations |
|
|
 |
Mezzanine Deck Structure
at Center P-tank Room |
|
|
 |
Coring Tube Installation
Structure Plans,
Sections and Details |
|
|
 |
Additional Pre-load Pump
Support Structure Plans,
Sections and Details |
|
|
 |
BOP Lift Ring for 50”
BOP/Diverter Plans,
Sections and Details |
|
|
 |
Leg mounted JIB
crane(5-Ton capacity)
Elevations, Sections and
Details |
|
|
 |
Stbd Burner Boom
Foundation Plan, Section
and Elevation |
|
|
 |
Preload Tank Hatch
Rescue Frame Elevation,
Section, Plans and
Details |
|
|
 |
ROV Room Hatch Cover
Plans, Sections and
Details |
|
|
 |
2-Ton Cargo Basket
Elevations, Sections and
Details |
|
|
 |
Yoke Weld Platform
plans, Sections and
Details |
|
|
 |
Weld shop Modifications
Plans, Sections, and
Details |
|
|
 |
Pontoon Cofferdam
construction |
|
|
 |
Analysis of the lift
ring & Creation of
Detailed Production
Drawings. |
|
|
 |
Modeling and FE Analysis
of LMRP’s Stab Plate |
|
|
 |
Prepare proper
construction drawings
for Rig’s mouse hole
using the reference
information. Change the
spring by fabreeca shock
Pads |
|
|
 |
Skid back arrangement of
drilling platform from
the one platform to
other. |
|
|
 |
As built drawing of
engine room trolley
beam. With calculations
for SWL of 12T. |
|
|
 |
Installation/foundation/
productions for putting
raiser booster pump. |
|
|
 |
Design and production
drawing of skimmer tank. |
|
|
 |
Design/calculation and
production of
installation of mud
cooler. |
|
|
 |
Production drawings of
Workshop for
mechanical/electrical
user |
|
|
 |
Production drawings of
Gym deck installation
under heli deck. |
|
|
 |
Production drawings and
structural analysis for
the removal of bow
thruster. |
|
|
 |
design and analysis of
fair lead |
|
|
 |
Design and analysis of
top drive for drilling
operation. |
|
|
 |
Simulation of hydraulic
system for the complete
operation of drilling.
Used for Computer based
training. |
|
|
|
Tools used |
|
|
|
|
 |
Excel |
|
|
 |
StaadPro |
|
|
 |
Soildworks/Unigraphics
(3-D modeling) & ANSYS |
|
|
|
|
 |
AutoCAD |
|
Feedback |
|
|
|
|
|
Very satisfied to
delighted. All projects